Update on 100 South Project

May 13, 2020:

Update on widening 100 South and adding roundabouts between Dan Jones and Reagan Parkway:

No final timeline as of today but we hope to have more information towards the end of May.

Right of Way is being purchased through the Court system.

Working on contribution agreement with Hendricks County since part of the road is not in Town.

Financing options are being reviewed.

New total project cost is estimated to be $20,485,000.