100 South Road Project Update: 5-26-20

Bid documents have been sent out to construction companies for the 100 South road widening project. Bids are due on June 25.

If the low bid is acceptable and gets awarded, the timeline involves utility relocation in 2020 along with replacement of the bridge, east of Dan Jones road. There may be a 75 day closure for the bridge replacement.

In 2021, starting possibly in March, 100 South from Dan Jones to Reagan Parkway will have a full closure. Limited access will be provided for properties that only have access from 100 South. Other properties that have access via another road will not have access to 100 South. At the end of 2021, the road is scheduled to open with two lanes of traffic and the remaining two lanes are scheduled to be completed in mid 2022.

If the bid is awarded, we will issue a more definitive timeline based on our meeting with the contractor.

The design for the project is located on our web site, www.avongov.org, in the public works section and we will post updates to the project, as well.